Skip to main content

Cracks in Miami bridge were documented 19 days before deadly collapse

Well before a deadly bridge collapse on March 15, a series of cracks had begun emerging on both the south and north ends of the new pedestrian bridge at Florida International University in Miami, the National Transit Safety Board says in a new preliminary report.

It says that cracks on the bridge’s north end were documented with photos a full 19 days before the failure that killed six people.

The significance of the cracking remains unclear. The investigation into the cause of the collapse of the 950-ton bridge could continue into 2019. The cracking has been a concern from the start, though the preliminary report shows the cracks had actually been noticed much earlier than had first been made public.

Two days before the bridge fell, the lead engineer on the project had left a voicemail with state officials saying cracking had been seen on the north end of the span that had been earlier moved into place during accelerated construction.

The engineer, W. Denney Pate with FIGG Bridge Engineers, had said that the crack was not a safety concern, according to a recording and transcript of the call released by the Florida Department of Transportation (FDOT). Safety issues had also been allayed during a meeting about the crack with the bridge design team and FDOT at the construction site just a few hours before the collapse, officials have said.

The NTSB continues to investigate the cracking as well as evaluate the bridge design, the construction process and the construction materials, the agency explains in the preliminary report released six days ago.

To read the full preliminary report, click here.

In the coming weeks, the NTSB says, it will be conducting additional forensic examination of several bridge structural components and destructive testing of multiple core and steel samples.

“All aspects of the collapse remain under investigation while the NTSB determines the probable cause, with the intent of issuing safety recommendations to prevent similar events,” the agency says.

Newly released photographic documentation from February 24, 2018 shows cracks already apparent at that time on the north end of the bridge.

Photographic documentation of the crack in the region of bridge diagonal 11 (north end).
Photos: Bolton-Perez and Associates Consulting Engineers, released by NTSB.

About 1:47 p.m that Thursday, the partially constructed pedestrian bridge crossing an eight-lane roadway in Miami experienced the catastrophic structural failure.

As a result, the 174-foot-long bridge fell about 18.5 feet onto SW 8th Street. Eight vehicles that had stopped below the bridge for a red light were fully or partially crushed. Seven of those vehicles were occupied, the report says.

One bridge worker and five people in vehicles were killed. Four more bridge workers and four other people were injured.

“The bridge was to be completed by early 2019 and was built using an accelerated bridge construction method—a technique intended to minimize disruption of traffic,” the report notes.

Five days before the collapse, the walkway, diagonals, and canopy comprising the bridge, which had been built in a lot adjacent to SW 8th Street, were moved from the lot, using transporters, into position across the roadway, then lowered onto bridge piers on either side of the roadway, NTSB says.

“Traffic on SW 8th Street was detoured during the installation period, and the entire roadway was closed to facilitate movement of the structure,” the agency notes of that Saturday work.

View of transporters moving the pedestrian bridge into place on the bridge piers. Photo: Florida International University, NTSB.

On March 10, in accordance with the bridge design plans, construction crew members de-tensioned the bridge diagonal members on the north and south ends of the bridge.

“When the collapse occurred on March 15, a construction crew was positioned on the structure working on re-tensioning the number 11 diagonal member connecting the canopy and the deck at the north end of the bridge,” the preliminary report says.

“Because a crane was being used for this work, two of the three westbound lanes below the north end of the bridge were closed to traffic; however, the five eastbound lanes remained open, and eastbound traffic was not detoured.”

The NTSB and assisting agencies are evaluating the emergence of the cracks in the region of diagonal members 2 (south end of the bridge) and 11 (north end of bridge). See figure 3 below to view the propagation of cracks in the region of diagonal member 11.

Elevation view of the pedestrian bridge in these drawings shows where the north-end cracking occurred. Refer to photos 1, 2 and 3 above this drawing for close-up details of the cracking on the north end. Source: Bolton-Perez and Associates Consulting Engineers, NTSB.

 



from Equipment World https://ift.tt/2kxLQqt
via Handy Rep Ai

Comments

Popular posts from this blog

Raleigh N.C. 540 outer loop faces environmental legal fight

The map above shows the 540 extension’s general location. Credit: NCDOT Environmental groups have filed a petition challenging the planned path of a future outer loop around Raleigh, North Carolina, due to concerns about the effect on nearby waterways that are home to endangered mussels. The $2.2 billion toll highway, an extension of N.C. 540, would complete the southern portion of an expressway outer loop. The construction contract for the first phase was awarded in December , and the N.C. Division of Water Quality recently issued an environmental permit for the project. The Southern Environmental Law Center , along with other environmental groups, is petitioning for an administrative hearing to challenge the environmental permit. The SELC says the proposed highway would “tear through 57,000 linear feet of streams and 70 acres of wetlands.” The groups are also concerned about increased stormwater runoff from the additional pavement from the highway, as well as more greenhouse em...

Indian Interior fit-out market-Opportunities for Construction Professionals

With the steady growth in the demand for the commercial real estate, the interior turnkey solution market has witnessed a progressive trend in their sector. As commercial space demand surges, the sector is expected to further witness a tremendous opportunity to leverage in coming years. Today, various start-ups, collaborative workspaces and other offices, be it an established business or a new company opt for complete fit-out services. As one-stop solution overcomes the hassle of limited time constraint, Turnkey is a perfect solution for all commercial interiors problems. Though start-ups and new offices make up an impressive portfolio, old and established companies too prefer refurbishing their interiors. Companies are focusing on their workspace design to increase employee satisfaction, boost productivity and provide a comfortable working environment. With the visible transition in the Indian work culture, office furniture and interiors have seen a major evoluti...

Walk-In Interview for Overseas on 2nd May 2018 | Travel Point HR Solutions India | 5 – 25 yrs | Chennai

Walk-In Interview on 2nd May 2018 at Chennai for Overseas Location Saudi Arabia  Candidates should be B.E/ B.Tech / Degree with Min 5 yrs of Exp Candidates from sea water Destination and power Production Walk-In Interview on Wednesday 2nd May 2018 Venue: Travel Point HR Solutions India APJ Buinesss center, 12 Haddows Road, Nungambakkam, Chennai Tamil Nadu – 600006 Contact : MS : Waseema – 9704675049 / 040-33151524                  Mr. Samee – 8886644854 / 040- 33151523 Email Address: e ngineers@travelpointhr.com Electrical Engineer 36 Openings Implementation of policies and procedure Supervising the working staff and updating the periodic maintenance schedule with the concerned parties as their polices following the programs and the working table of preventing maintenance Achieving and following repairing works and the daily maintenance to secure that they matching the required quality according the stander maint...